The Pre-Production Begins!

It’s all starting with the building of a green screen with a ramp transition. This is huge, and will have a lot of uses.

The transition is finished!
5.15.08
Start of the Day
Ramp Skeliton
Plastic to keep out the elements.

Bracing to keep the wall flush with the ramp.

Bracing Detail

Almost Done! Thanks Adam!
5.18.08
Finishing the Wall
Ryan’s going crazy!
Lining up the last pannel

Finishing the install

…and the wall is finished. Now its time to build the floor structure. New plans will be coming for that shortly. Thanks for your help Ryan!
5.28.08
floor structure.A bit dusty…hopefully we can pull it all out before shooting!
The floor is almost finished. it makes a lot of noise when walking on it, so we the hunt begins for cardboard to fill the gaps. Hopefully it will suck up the noise, we’ll see!
6.2.08
Construction Finished!
Here it is, with a removable 4′x12′ section (not that even =/ )
The tape has been peeling off, probably due to dust and humidity. Perhaps wall paper will work.

Mind the Gaps.
6.2.08
First Coat
Some more minor patch work needs to be done, but the next coat should be done by mid-week.
6.11.08
FINISHED!
The paint is still a bit wet, and the color is off in this image…but it is DONE!
the extension is pulled out, but together its matched well. LET THE PRODUCTIONS BEGIN!